City of Carrabelle
Water System Evaluation for
Carrabelle and Alligator Point Water Systems
CDM Project 48049-74094
Kickoff Meeting Agenda
September 20,
2010
10:30 a.m.
Carrabelle City Offices
I.
PROJECT OVERVIEW
A.
Project Purpose: City of Carrabelle and APWRD intend to
cooperatively evaluate a mutually beneficial interconnected water system
to serve current and future customers. The NWFWMD has identified the
area of study as an Area of Special Concern and is funding this project
in order to develop long-range options for regional water supply. The
evaluation will include technical feasibility, economic feasibility and
community acceptance.
B.
APWRD Status
C.
Carrabelle Water System Status
II.
PROJECT TEAM
A.
City’s Project Manager – Courtney Dempsey
B.
City’s Project Administrator – Keisha Smith
C.
CDM’s Project Manager - Lynne Putnam
D.
CDM’s Project Administrator - Melissa Ward
E.
Alligator Point Water Resources District (APWRD) Project
Representative – Skip Cook
F.
Northwest Florida Water Management District (NWFWMD)
Representative – Paul Thorpe
III.
CONTRACT SCOPE OF WORK
A.
Kickoff Meeting
B.
Data Collection
C.
Water System Hydraulic Analysis:
1.
Hydraulic Analysis of two routes/sources for current and future
water supplies and demands.
2.
Draft TM1 – Hydraulic Analysis Results with routes and
preliminary costs.
3.
Final TM1 – with City, APWRD, and stakeholder input.
D.
Stakeholder Workshops
1.
TM1 Review and Development of Decision Criteria Meeting
2.
Draft Water Systems Evaluation Report Review Meeting
E.
Funding Analysis – identify funding sources and approaches to
implement project.
F.
Water System Evaluation Report will include
1.
Summary of TM 1
2.
Criteria Developed with Stakeholders
3.
Alternatives Analysis
4.
Funding Analysis
5.
Draft Water System Evaluation Report
6.
Final Water System Evaluation Report
G.
Project Management
H.
Schedule: Technical Kick-Off meeting held June 24, 2010
Draft TM 1 issued
September 30, 2010
Next Stakeholder
Meeting week of October 11, 2010
Final TM 1 published
October 29, 2010
Draft Water System Evaluation
Report issued November 30, 2010
Final Stakeholder
Meeting week of December 13, 2010 (maybe earlier)
Final Water System Evaluation
Report published January 2011
|